1. Project Plan
(1.1)The
Define Phase
(1.11) Introduction:
· Write
a statement describing the overall purpose of the project.
·
What is the key challenge or problem the
project is aiming to address?
· What
are students intended to learn from the project?
The project is intended to allow class VIII students to explore the
following topics
The students will work in small group to acquire the knowledge about
the need and importance of conserving rain water. It also helps them to
develop 21st c skills.
|
(1.12) Project
Scope:
Describe the scope of your
project. This may include class and section, subjects it covers, soft skills to
be used etc. as well as other factors affecting scope.
Student class VIII TOPIC :RAINWATER HARVESTING
Topic involved: science, technology, maths, sociology, geology student’s
research will be monitored by the mentor.
|
(1.13) Curriculum
and Standards:
List the curriculum and
standards this project with cover.
Class VIII,
social studies Curriculum topics and standards related this project
What is rainwater harvesting.
Need and importance.
Outcome of lack of storage of rainwater.
|
Project Based Learning
Lesson 2
2.1 Essential
Question:
Put in writing the
question that will engage the students
How can we save monsoon rainwater for future needs and to protect the
ecosystem?
|
2.2 Grouping
Strategy:
Describe
the criteria that will be used to form student’s team and how this maps to the
goals of the project.
Team will comprise groups of students mixed with
gender and mixed ability and skills as well as varied social and economic
backgrounds the team members will get opportunity for interaction with peer
groups as also to develop their self-confidence and ability of public
speaking by giving them a chance to present their project finding in front of
their class.
|
2.3 Learning
Environment:
Describe
the learning environment for the project including any classroom adaptation
that will be required.
A group working
area in the classroom will be set aside with tables and chairs to allow more
effective interaction among team members. A classroom wall near the project
area will be set aside to post paper materials collected during research notes
will be converted to documents that the team can record this in computer the
team members also collaborate via mail as is required.
|
2.4 Assessment
Approach:
Describe the approach for:
2.41 Authentic Assessment:
Why rainwater harvesting?
Study the quality
of drinking water in the villages.
What are the
benefits of rain water harvesting to environment.
|
2.42 Formative
Assessment:
Regular feedback and guidance as
and when required will be provided to the students as they work with the
various tools of the project- online research surveys and presentations etc
and also prepare the materials for peer talks.
|
2.43 Summative Assessment:
Assessment will be conducted on
·
The quality of
the rain water in kerala
·
Different
methods of collection
·
Storage
facilities
·
Benefits on
environment.
|
2.44 Rubrics:
Rubrics will be used to asses
·
Survey and
collection of data
·
Report based
upon comparison
·
Power point
presentation
|
2.45 Gradings:
Project grades
will be based on a combination of scores from assessments made during the
project period. It will include accuracy of interpretation of data and
effectiveness of presentations
|
Project Based Learning
Sample – Lesson 3
Plan Phase
3.1 Work
Breakdown, Products and Milestones:
List the project task
and, if possible at this stage include the sub-tasks. For each task add the
product that will be created and indicate it will be a milestone.
Class room instruction : Needs and importance of rain water
harvesting
Select student group :
Students group
Research
: Online and research work from library materials.
Activity
: Collection of data from library, field trips.
Class activity
: Peer talk.
|
3.2 Role
definition:
List the roles team members
will fulfill in the project.
Project Leader
: Teacher
Researcher/ Survey Writer :
All students.
Presentation
: All students will take some role in presentation.
|
3.3 Task
schedule:
Note start and end dates for
the project.
Include
expected dates to start specific tasks
Project start Date : 10-08-2016
Project end Date : 30-11--2016
|
3.4 Special
Activities Plan:
List
any special activities (e.g. Field trips or guest speakers) including dates.
Field trip to visit a rain water
harvesting area.
|
3.5 Resource
Plan:
List resource that will be
required during the project and any other date constraints associated with
them.
Computer Lab & Library facilities.
One period per one week.
|
3.6 Direct
Instruction:
List any planned direct instruction sessions and link them
to specific tasks if appropriate.
Conduct a survey of houses near the rain water storage areas to
compare with other normal areas.
|
3.7 Reviews
and checkpoints:
Describe how you will incorporate review meetings and
checkpoints in the project
30 minutes class time every week to discuss the progress of the task
taken up and problems encountered by them.
5 Minutes meeting with each group separately twice a week.
|
3.8 Assessment
plan:
Describe the balanced assessment plan for the project. List
products that will be assessed during the project. List rubrics that need to be
created before project launch.
Opportunities for authentic assessment will include the survey and
its result.
Formative assessment will primarily focus on the
data and conclusions reached by the children.
Special attention will be paid to survey reports, learning journals,
presentation of outline.
Summative assessment will be performed on the basis of survey
results.
Rubrics will be prepared to assess the end result.
|
Work plan-Lesson 4
Prepare
work plan in the format given below.
Sl.
No
|
TASK
|
SUBTASK
|
ROLE
|
START DATE
|
END DATE
|
PRODUCT
|
01
|
Launch project
|
10.08.16
|
30.11.16
|
Project launched
|
||
02
|
Deliver classroom instruction
|
Areas
to be covered.
1.Define
the project
|
Teacher
|
11.08.16
|
11.08.16
|
Initial classroom instruction is completed
|
03
|
Group selection
|
Students’
list
|
Teacher
|
12.08.16
|
12.08.16
|
Group selection is completed
|
04
|
Conduct research
|
Collection
of data about Rain Water Harvesting.
2.Collect
data about the Rain fall in Kerala
|
Student
|
12.08.16
|
20.10.16
|
Students recorded in the computer
|
05
|
Field Trip and Survey
|
Conduct
survey, prepare survey report
|
Student
|
25.10.16
|
30.10.16
|
Collected report
|
06
|
Programme sheet activity
|
Prepared
report based on data.
|
Student and teacher
|
30.10.16
|
05.11.16
|
Prepared
|
07
|
Advice meeting
|
Team
prepare briefs
|
All team members
|
06.11.16
|
06.11.16
|
A meeting was held
|
08
|
Programme sheet presentation
|
Presentation
|
All team members
|
08.11.16
|
10.11.16
|
Presented
|
09
|
Preparation of questionnaire
|
Eliciting
from peer group and analysing
|
Each member
|
12.11.16
|
12.11.16
|
Prepared questions
|
10
|
Project presentation
|
Posting
in the computer/blog
|
All
|
15.11.16
|
18.11.16
|
Completed
|
11
|
Assessment and grading
|
Prepare
rubrics and assessment
|
Teacher
|
19.11.16
|
19.11.16
|
Completed
|
12
|
Refection and evaluation
|
Student
reflection and evaluation, Teacher refection and evaluation
|
Students and teacher
|
20.11.16
|
22.11.16
|
Completed.
|
13
|
Project closed
|
Submitting
to the Principal
|
Teacher
|
30.11.16
|
30.11.16
|
Closed
|